Dedicated Freight Corridor

August 2020

Sector: Railways Length: 9,129 km (EDFC: 1,856 km; WDFC: 1,504 km; three new corridors: 5,769 km) Investment: Rs 2,596 billion (EDFC: Rs 303.58 billion; WDFC: Rs 511.01 billion; three new corridors: Rs 1,781 billion) Implementing […]

Kerala Semi-High Speed Rail Corridor

August 2020

Sector: Railways Length: 529.45 km Investment: Rs 639.41 billion Ownership: Government (central and state) Implementing agency: Kerala Rail Development Corporation Limited (K-Rail) Mode of implementation: Yet to be decided Expected completion: 2025 A silver lining […]

Mumbai-Ahmedabad HSR Corridor (Silver Line)

August 2020

Sector: Railways Length: 508.17 km Investment: Rs 1,080 billion Ownership: Government (central and state) Implementing agency: National High Speed Rail Corporation Limited Mode of implementation: EPC Start date: September 2017 Expected completion: December 2023 The […]

Station Redevelopment Programme

August 2020

Sector: Railways No. of stations: 600 stations Investment: Rs 1,000 billion Ownership: Government (central and state) and PPP (50 stations) Implementing agency: Indian Railway Station Development Corporation Mode of implementation: EPC (Gandhinagar, Chandigarh, AnandVihar, Bijwasan, […]

Mumbai Metro

August 2020

  Sector: Urban rail Length: 223 km Investment: Rs 1,013 billion Ownership: Government (state) Implementing agency: Mumbai Metropolitan Region Development Authority, Mumbai Metro Rail Corporation Limited (Line 3) Mode of implementation: EPC Start date: 2016 […]

New Port at Vadhavan

August 2020

Sector: Ports Capacity: 10 million TEUs Investment: Rs 655 billion Ownership: PPP Implementing agency: Jawaharlal Nehru Port Trust (JNPT) and Maharashtra Maritime Board Mode of implementation: PPP Start date: Yet to be decided Expected completion: […]

Chennai Metro Phase II

August 2020

Sector: Urban rail Length: 119 km Investment: Rs 692 billion Ownership: Government (central and state) Implementing agency: Chennai Metro Rail Limited (CMRL) Mode of implementation: EPC Start date: Yet to commence Expected completion: 2025-26 Chennai […]

Vadodara-Mumbai Expressway

August 2020

Sector: Roads Length: 447 km Investment: Rs 400 billion Ownership: Government (central) Implementing agency: NHAI Mode of implementation: Hybrid annuity model (HAM) Start date: March 2019 Expected completion: 2023 The Vadodara-Mumbai section of the proposed […]

Delhi-Vadodara Expressway

August 2020

Sector: Roads Length: 845 km Investment: Rs 424 billion Ownership: Government (central) Implementing agency: National Highways Authority of India (NHAI) Mode of implementation: EPC Start date: March 2019 Expected completion: 2023 The Delhi-Vadodara section of […]

Manufacturing-Linked Solar Project

August 2020

Sector: Power Capacity: 8,000 MW Investment: Rs 450 billion Ownership: Private Location: Multiple Implementing agency: Adani Green Energy Limited (AGEL) Start date: June 2020 Expected completion: 2025 As part of its first-of-its kind manufacturing linked […]

Mission Bhagiratha Water Grid Project

August 2020

Sector: Water and waste Length: 146,000 km Investment: Rs 450.28 billion Ownership: Government (state) Implementing agency: Telangana Drinking Water Supply Corporation Limited Mode of implementation: EPC Start date: September 2015 Expected completion: NA The Mission […]

Andhra Pradesh Water Grid Scheme

August 2020

Sector: Water and waste Investment: Rs 466.75 billion Ownership: Government (state) Implementing agency: Andhra Pradesh Drinking Water Supply Corporation Mode of implementation: EPC Expected completion: December 2022   In October 2019, the Andhra Pradesh government […]

Bharat  Net Project

August 2020

Sector: Telecom Scope: Fibre connectivity to 250,000 gram panchayats Investment: Rs 450 billion-Rs 500 billion Ownership: Government (central) Implementing agency: Bharat Broadband Network Limited (BBNL) Mode of implementation: EPC and non-EPC (Phase II) Start date: […]

Mumbai-Nagpur  Expressway

August 2020

Sector: Roads Length: 701 km Investment: Rs 553 billion Ownership: Government (state) Implementing agency: Maharashtra State Road Development Corporation (MSRDC) Mode of implementation: EPC Start date: August 2018 (first set of 13 packages awarded) Expected […]