About 85 per cent of construction work has been completed on the Panvel-Kasu Four Laning Highway project (NH-66) (Panvel-Indapur stretch Balance Works). Of the total 40 km, around 39 km of road concretisation has been completed. While, of the 23.7 km of parallel service road concreting, approximately 9 km has been finished.
Additionally, vehicular underpass work at Gadab in Pen taluka is also progressing. Besides, 45 per cent work on Kasu-Indapur Four Laning Highway project (NH-17) (Package-II) has been completed.
Both projects are likely to be completed by December 2024.