Larsen and Tobbro Limited (L&T) has completed 3,066 piles for the section between Nehru Nagar and Sholinganallur along Old Mahabalipuram Road (Corridor III)under the Chennai Metro Rail Project Phase II. It has also completed the casting works for 582 precast prestressed U-Girders.
The Phase II Project involves development of 118.9 km three metro corridors (Corridor III, IV and V) in Chennai city of Tamil Nadu at an estimated cost of Rs 632.46 billion. It is mostly underground with an elevated section confined to a few short stretches and consists of 128 stations in total.