Supply Surplus: Surge in coal production poses new challenges

Surge in coal production poses new challenges

Until a couple of years ago, shortage of coal was one of the biggest challenges that the power sector was grappling with. However, a slew of reforms over the past two years have dramatically transformed the country’s coal landscape. Coal India Limited (CIL), the country’s largest coal producer, has had a dream run in terms of production. It registered a 6.9 per cent growth in output in 2014-15 and growth in 2015-16 was even better at 8.6 per cent.

With the improvement in domestic coal supplies, imports have started showing a decline, with a 9 per cent reduction being reported in 2015-16 over 2014-15. Coal supply at thermal power plants (TPPs) has reached an all-time high and none of the TPPs has reported any critical or supercritical coal stock positions.

There is now in fact a situation of oversupply of the fuel. Low coal offtake by power companies and other industries has led to rising coal inventory levels both at TPPs as well as CIL’s pitheads, well beyond optimum levels. According to Anil Razdan, former power secretary, “In the past year, even without meeting the annual target of 550 million tonnes (mt) and attaining a production of about 538 mt, CIL had unsold stocks of around 50 mt.”

In order to deal with the problem of oversupply, the possibility of coal exports to neighbouring countries is being examined. Further, production has also been cut back. Given the declining demand, the coal production target of 1 billion tonnes (bt) by 2020 seems too ambitious, warn industry experts.

However, a major cause for concern is that despite increasing coal supplies, challenges for the power sector do not seem to be ending. There are still many power plants that have been meeting a part of their coal requirements through imports or e-auctions. According to industry experts, this is distorting tariffs and hence increasing stress in the sector.

What are the factors that have led to coal oversupply? Why is the power sector still reeling under shortages? Indian Infrastructure takes a closer look at some of these issues affecting the demand-supply dynamics of the coal market…

pg-23-a

Changing coal scenario

The primary reason for the excessive coal stock has been CIL’s record production in the past two years, without a commensurate increase in coal demand.

“CIL deserves credit for its performance on the production front. However, demand has not really picked up as expected, probably due to lower-than-expected growth in power generation, which in turn is due to lower-than-expected industrial growth. Also, the precarious financial health of distribution companies has led to subdued electricity demand,” says Dipesh Dipu, partner, Jenissi Management Consultants.

CIL’s production was almost stagnant between 2009-10 and 2011-12, while in the two years that followed, production improved slightly, but was still less than 4 per cent.

In 2014-15, surpassing all records, CIL registered a growth of around 7 per cent, producing 494.2 mt. In 2015-16, CIL’s coal production further increased by 8.6 per cent to reach 538 mt, the highest in the past 10 years. The company’s coal production target for 2016-17 is 598.61 mt, a jump of over 11 per cent.

The increase in coal production has been due to a combination of factors including the close monitoring of select projects, faster environmental clearances for new projects, timely closure of important tenders, as well as better coordination between the central and state authorities. In addition, outsourcing production to private entities through mine developer and operator agreements has contributed to the growth in production.

In contrast, demand has failed to pick up commensurately. Coal offtake during the April-June quarter of 2016-17 increased by only 2.9 per cent year on year as compared to CIL’s production growth of 9 per cent. With 90 per cent of CIL’s supplies being for the power sector, the thermal power segment is one of the key growth drivers for the company. With plant load factors having come down to 60 per cent, the coal requirement of power stations has reduced significantly.

As of end-July 2016, the coal stock available with thermal power stations for 22 days stood at over 30 mt. In comparison, two years ago (end-July 2014), power stations reported coal stocks aggregating less than 10 mt for just seven days.

With the improved coal production, there was a reduction in imports last year. While coal imports increased at a compound annual growth rate of 21 per cent between 2010-11 and 2015-16, they fell from 217.78 mt in 2014-15 to 199.88 mt in 2015-16.

According to Piyush Goyal, Minister of State (Independent Charge) for Power, Coal and New and Renewable Energy, “The declining trend in coal imports continues in 2016-17. For the period April-May 2016, coal imports reduced by around 5 per cent as compared to the corresponding period of the previous year.” Coal imports are projected to reach 160.16 mt in 2016-17.

Challenges remain for the power sector

Despite a considerable improvement in coal supplies, stress in the power sector has failed to ease. Some generation plants are still without firm linkages or operational coal blocks, and are thus procuring coal through the market to meet their requirements.

“There are still some thermal power stations which have to get coal through e-auction or imports, depending upon their location and logistics. Although the price differential between e-auction and linked coal has reduced, it adds to the cost of power and tariff for the consumer. In my opinion, this differential is not justified in a situation where CIL is the monopoly producer and has reported large unsold stocks. This is an anomaly,” says Razdan.

The issue stems largely from a policy overhang of the previous government. Back in 2013, when the coal supply situation was grim, the Ministry of Coal (MoC) had directed coal companies to supply coal to some power plants through the short-term MoU route till their fuel supply agreements-related issues were resolved.

However, in light of the improved supply situation, the MoC had earlier this year issued a notification which states that power producers which are being supplied coal by CIL through the MoU route will now have to take it through e-auctions, as the government has decided not to extend the MoU route mechanism beyond June 30, 2016.

Reportedly, there is around 14,600 MW of capacity which is being supplied coal through the MoU route. Most of this capacity (around 13,000 MW) has power purchase agreements (PPAs) in place. According to experts, the proposal to ask these plants to switch from the MoU route to e-auctions is creating difficulties. “Coal supply through e-auctions is not a viable alternative for long-term PPA holders with price commitments for 25 years, considering the variability in pricing and uncertainty of quantum, as each time the developer has to assess backwards to see the price that he can offer. Besides, it may result in under-recovery, as the penalty for not supplying power is huge. This is adding to the power sector stress,” says Ashok Kumar Khurana, director general, Association of Power Producers.

Further, if these power producers are required to participate in the proposed coal linkage auctions, they would suffer under- recoveries under the existing PPAs. “Looking at the comfortable coal supply position, it is an opportune time for the government to relax the restrictive coal allocation framework, which was imposed at the time of scarcity. This would send correct signals,” Khurana adds.

pg-23-b

Addressing the oversupply situation

CIL’s coal inventory levels reported an increase of around 4.2 mt between April 2015 and March 2016, and the year ended with an inventory of about 58 mt. The company has been in a slowdown mode owing to concerns over stockpiling and stock management problems (including deterioration in the quality of piled-up coal and risk of spontaneous combustion).

The company undertook production cuts in 2016-17 and achieved only 90 per cent and 95 per cent of its monthly production targets for April and May 2016 respectively. In the first two months of 2016-17, its cumulative coal production was nearly 83 mt, which remained flat as compared to last year.

In addition, CIL is finding it difficult to find sufficient buyers on the e-auction platform. In July 2016, only 68 per cent of the coal offered under e-auction found takers, compared to July 2014, when the corresponding figure was at around 90 per cent. Meanwhile, the coal major is exploring options of exporting coal to neighbouring countries on a commercial basis, as indicated by the MoC. Traditionally, coal has been exported to Bhutan, Nepal as well as Bangladesh as part of bilateral trade agreements with these countries. However, quantity-wise these exports have been negligible.

CIL is reportedly planning to enter the Bangladesh market by supplying coal to the 1,320 MW Maitree project, which is being set up in a 50:50 joint venture between India’s NTPC Limited and the Bangladesh Power Development Board. The project’s annual coal requirement is around 6 mt.

According to media reports, CIL plans to supply coal to Bangladesh-based power companies from two of its subsidiaries, Bharat Coking Coal and North Eastern Coalfields, via the sea route.

The Bangladesh market, which currently buys around 3 mt of coal a year, would be a lucrative export opportunity for CIL. As per research firm Wood Mackenzie, demand could jump to as much as 15 mt by 2020 as planned power plants worth $8 billion are being set up in the country with help from India and China. Further, CIL’s coal is likely to be cheaper as compared to Indonesian coal due to market proximity.

Meanwhile, industry experts are of the opinion that the current oversupply situation is the right time to improve the quality of coal, reduce the cost of production, improve productivity as well as reduce the prices of unwashed coal. Moreover, the strict enforcement of inventory methods such as first in, first out will help minimise the deterioration of inventory.

pg-24Outlook

With no takers for domestic coal at present, the key question is whether the coal production target of 1 bt by 2019 is overambitious. In May 2015, CIL released a roadmap for 2020 providing the list of planned projects (535 mines) which add up to 908 mt – 165 mt from existing operational projects, 561 mt from projects under implementation and 182 mt from future projects.

“CIL will have to reconsider its targets. Even if the anticipated growth materialises, it would come at a lower base and, therefore, the trajectory will have to be revised downwards if market equilibrium is to be maintained,” states Dipu.

According to Razdan, “CIL cannot keep ramping up coal production, regardless of domestic demand. Production schedules of CIL have to be tweaked so as to meet the demand.”

In sum, the improvement in coal supplies is certainly an achievement worth celebrating. However, efforts to address the problems of oversupply and coal availability need to be stepped up to prevent this positive from becoming a negative for the power sector.