Jyoti Structures Limited has announced the successful completion and commissioning of the 400 kV Gadag-II transmission line project in Karnataka for its client, ReNew Power.
The project comprises about 100 circuit km of twin high-temperature low-sag transmission line between the Gadag pooling station and Koppal pooling station. The project forms part of the inter-state transmission system for evacuation of power from the 1,500 MW Koppal Solar Energy Zone and supports renewable energy evacuation in the state.