NLC India commissions second phase of 300 MW solar project in Bikaner, Rajasthan

NLC India Limited has commissioned the second phase of a 300 MW solar power project, with a capacity of 106 MW at Barsingsar in Bikaner district, Rajasthan.

The commissioning certificate was issued by Rajasthan Renewable Energy Corporation Limited. The first phase of 52.83 MW had already commenced commercial operations on August 26, 2025. With this, the total capacity under commercial operation now stands at 158.83 MW out of the planned 300 MW.