About 90 per cent casting work completed on Redevelopment of Nagpur Railway Station Project in Maharashtra 

Rail Land Development Authority (RLDA) has completed about 90 per cent casting work for Phase-2 of the basement construction for the Redevelopment of Nagpur Railway Station Project in Maharashtra. Besides, excavation and foundation work have been completed on the same.

The project involves major upgradation of the Nagpur railway station in Maharashtra with an investment of Rs 4.87 billion.