304 km viaduct installation completed on Mumbai-Ahmedabad HSR Corridor Project in Maharashtra, Gujarat 

National High Speed Rail Corporation Limited (NHSRCL) has completed 304 km of viaduct installation work on the Mumbai-Ahmedabad High-Speed Rail (HSR) Corridor Project. Furthermore, 388 km of pier work, 14 river bridges, 7 steel bridges, and 5 prestressed concrete (PSC) bridges and 163 km of trackbed construction have been completed under the project.

The project involves development of the 508.17 km long Mumbai-Ahmedabad HSR corridor in Maharashtra and Gujarat with an investment of Rs 1,080 billion.