Nagaland’s 468.71 km highway projects progress with Rs 77.11 billion investment 

As per the National Highways and Infrastructure Development Corporation (NHIDCL), around 25 national highway projects covering 468.71 km in Nagaland are progressing, with a total investment of Rs 77.11 billion. This includes the delayed four-laning of the Dimapur-Kohima Road on NH-29 under the SARDP-NE initiative. Of its three packages, only Package-II (13.71 km) is fully completed, while Package-I (14.94 km) near Pagla Pahar is completed but pending certification. Frequent rockslides continue to impact this stretch, with landslides in September 2024 damaging road sections.

For Package-III (14.21 km), which includes the Dzüdza area, work is 16.82 per cent complete and expected to be operational by September 2025. The Dimapur Bypass connecting NH-29 is projected to be completed by December 2024, while the Kohima-Mao road upgrade on NH-2, at 74.23 per cent progress, is scheduled for completion in February 2025.