Construction work on Unit-4 of Chandu Budhera Water Supply Project to complete by January 2025 in Haryana

The construction work on the Chandu Budhera (Gurugram) Water Supply Project (Unit 4) is likely to be completed by January 2025. Currently, about 80 per cent of the work has been completed.

The scope of work involves the augmentation of a water treatment plant (WTP) by constructing a 100 million litre per day capacity Unit-4 WTP to meet the water supply demand from sectors 81 to 115 in Gurugram. This is being implemented under phase I of the project at an estimated cost of Rs 700 million.