The construction work on Anand Vihar-Apsara Flyover Project is expected to be completed by June 2024.
It was earlier expected to be completed by April 2023, however, the work has been delayed due to construction ban imposed due to the graded response action plan (Grap) in November 2023. The project involves construction of 1.4 km long six lane flyover connecting Apsara border and Anand Vihar at a cost of Rs 3.72 billion.