The international airport at Halwara is 90 per cent complete and is set to be ready by September 30, 2023. The works related to integrated civil enclave and cargo terminal at the Air Force station in Halwara is set to be ready by the said date. The allied works are targeted to be completed by October 31, 2023. The balance work was earlier scheduled to be completed by September 12, 2023. These include the apron and taxiway which are 25 per cent complete each, and the internal road, lighting and public health works are 55 per cent complete.