1.5 km tunnel work completed on Anand Vihar-New Ashok Nagar stretch of Delhi-Meerut RRTSS

Work on the 1.5 km-long tunnel on the Anand Vihar-New Ashok Nagar stretch of the Delhi-Ghaziabad-Meerut Regional Rapid Transit System Project Phase I has been completed. A tunnel boring machine (TBM) designated Sundarshan 4.1, is excavating on the stretch. Meanwhile, Sundarshan 4.2 has bored a 1 km stretch of the parallel tunnel. Moreover, Sundarshan 4.3 has commenced tunnelling work while Sundarshan 4.4 is yet to commence work on the 2 km-long parallel tunnels on the Anand Vihar-Sahibabad stretch.