Ghatampur Supercritical TPP

 

Sector: Power

Capacity: 1,980 MW

Investment: Rs 172 billion

Ownership: JV (central and state governments)

State: Uttar Pradesh

Implementing agency: Neyveli Uttar Pradesh Power Limited

Start date: August 2016

Expected completion: 2021-22

 

The 1,980 MW (3×660 MW) Ghatampur project marks public major NLC India’s first thermal power venture outside Tamil Nadu. Being implemented by Neyveli Uttar Pradesh Power Limited, a JV of NLC India and Uttar Pradesh RajyaVidyutUtpadan Nigam Limited with a 51:49 equity participation, the supercritical project entails an investment of Rs 172 billion, of which Rs 95 billion has been incurred so far. The Pachwara South coal block has been allocated to meet the fuel requirement of the project. The order for equipment has been placed with L&T-MHPS and Alstom-Bharat Forge Power Limited. The project’s Unit 1 is expected to be commissioned in November 2020, Unit 2 in May 2021 and Unit 3 in November 2021.