The CCEA approved three railway line projects in Assam and Uttar Pradesh on July 17, 2019. These are the New Bongaigaon-Agothri line doubling project, the Allahabad-Mughalsarai third rail line project and the Sahajanwa-Dohrighat new rail line project. The New Bongaigaon-Agothri project involves doubling of a 142.97 km rail line between New Bongaigaon and Agthori in Assam at an estimated cost of Rs 20.42 billion and is expected to be completed by 2022-23. In Uttar Pradesh, the CCEA has approved the development of a 150 km third railway line project between Allahabad and Mughalsarai at an estimated cost of Rs 26.49 billion and a 81.7 km railway line between Sahajanwa and Dohrighat at a cost of Rs 13.19 billion. The projects are expected to be completed by 2023-24. Further, the CCEA granted approval for the Vaibhavwadi-Kolhapur new railway line project on August 5, 2019. The project involves construction of a 107.76 km rail line between Vaibhavwadi and Kolhapur in Maharashtra at an estimated cost of Rs 34,385.1 million. It is expected to be completed by 2023-24.