MoRTH completed construction of 6,604 km of national highways till February 2017

The MoRTH has completed the construction of 6,604 km of national highways from April 2016 to February 2017. The target of construction of national highways during 2016-17 is 15,000 km. The slow speed of construction is mainly due to delays in land acquisition and utility shifting, the non-availability of soil/aggregates, poor performance of contractors, delays in environmental/forest/wildlife clearances, rail overbridge and underbridge issues with IR, public agitation for additional facilities, arbitration/ contractual disputes with contractors, etc.